Why Pre-Shipment Machine Testing Matters

2026-07-17 Last Updated: 17/07/2026 13 min read Machine & Technology Guides
Author: Later Wang

Production Line Planning & Project Management

Later Wang oversees production line planning and project management at Strivers Machinery, coordinating equipment configuration and delivery timelines to match each client's manufacturing goals.

WhatsApp  |  Email

Reviewed by Sunny Sun

International Project Coordinator & Global Customer Support

Factory acceptance testing of industrial machinery before shipment to verify equipment quality and production performance.
Quick Summary

This guide explains:

  • ✔ FAT checks whether the supplied machine meets agreed requirements before shipment, using recorded conditions and acceptance criteria
  • ✔ Use representative product and packaging, and document the limits of substitute materials
  • ✔ Review fill results by head, continuous-run records, protective functions, changeovers, and open issues
  • ✔ The project examples show commissioning delay after limited checks and a timing fault corrected before shipment
  • ✔ Complete site installation and SAT to verify the equipment with the customer’s actual utilities and production conditions
Key Takeaways
  • ✔ Manufacturing quality, useful testing, and proper installation all contribute to reliable production
  • ✔ Agree test scope, materials, speed, duration, sampling, and pass/fail limits before FAT
  • ✔ Water can support selected checks; representative cream or other product is needed for the relevant filling assessment
  • ✔ Record individual-head results and actual stops, alarms, rejects, and adjustments during sustained running
  • ✔ Project-specific testing and commissioning times should remain identified as project results
  • ✔ Close issues through documented correction and retesting, with written treatment of any open items
  • ✔ Keep the accepted configuration, appropriate software backups, and site acceptance records together

Factory Acceptance Testing, or FAT, checks whether a machine meets the agreed requirements before it ships. For a filling machine, that means checking the product, containers, fill results, controls, and sustained operation under recorded conditions. It gives the buyer evidence to review while adjustments can still be made in the supplier’s workshop.

Good FAT can reduce surprises during installation. Site Acceptance Testing, or SAT, then checks the equipment in the customer’s actual installation. Plan both stages before ordering, with clear test conditions and pass/fail criteria.

A Filling Machine Is Only Valuable When It Runs Reliably in Your Factory

Assembly produces the machine. Testing shows how it performs under the conditions you agreed. Both matter. A good weld, a suitable seal, and a correctly timed filling cycle each contribute to a machine that is ready for production.

Project referenceContext
May 2025 — South American customer visitFactory inspection in Guangzhou; discussion of a servo piston filling machine for cosmetic cream
August 2024 — Indonesian cosmetic OEM projectEarly shipment after basic checks; planned two-day commissioning extended to nearly two weeks
Continuous-run fault and retestIntermittent timing difference at the eighth filling head; parameter adjustment and a further six-hour run

“It’s Just Assembly and Welding.” A Conversation That Changed the Discussion

A Factory Visit We Still Remember

In May 2025, a purchasing manager from a cosmetics factory in South America visited Strivers Machinery to inspect an order before shipment. Walking through the assembly workshop, he watched a stainless steel filling machine taking shape and said:

“It’s just assembly and welding.”

It was a useful starting point for a discussion. Cutting steel, welding a frame, fitting components, and installing controls are visible tasks. The next question is whether those parts work together with the customer’s product and packaging, at the required output.

The Real Product Includes Production Reliability

A customer needs stable filling, manageable cleaning, practical maintenance, and predictable output. Those requirements belong in the purchase specification. Our cosmetic equipment buying guide explains how to turn a production need into questions a supplier can answer and test.

Welding and assembly quality remain part of that assessment. Smooth, accessible product-contact surfaces help cleaning, while secure mounts and good alignment support repeatable motion. The equipment cleaning dead corners guide covers details that a short running demonstration can miss.

The Hidden Cost of Skipping Proper Testing

A Real Project from a Cosmetic Factory in Southeast Asia

In August 2024, a cosmetic OEM manufacturer in Indonesia requested early shipment to meet a product launch. The factory’s reported production capacity was 180,000 bottles per day. This was factory-level context, not a measured output claim for the individual filling machine.

Only basic power-on and no-load checks had been completed before shipment. Once the machine was installed and ran high-viscosity skincare cream, several problems appeared: differences between filling heads, nozzle dripping, servo synchronization errors, and conveyor positioning that affected downstream capping alignment.

The planned two-day commissioning period became nearly two weeks of troubleshooting. Test product was consumed during repeated runs, engineers worked on site, and the production launch was delayed. These are the results of this project; other installations have different site conditions and schedules.

The Cost Extended Beyond the Machine

The delay affected production planning, engineering time, materials, and customer orders. It also left operators waiting for equipment that was not ready. Our hidden equipment costs guide explains how to include these tasks and risks in the project budget.

Early shipment can still be a commercial decision, but the buyer needs to see what remains untested. Record the open items, possible production effect, responsibility for completion, and any agreed release conditions. A shipment date is easier to assess when the remaining work is visible.

Why We Spend Days Testing Before Shipment

Assembly Is Only the Beginning

After assembly, Strivers Machinery checks equipment against its agreed inspection and test scope. The exact plan varies with the machine and project. A servo piston filler needs product and dosing checks that differ from those for a conveyor, capper, or water treatment unit.

Recommended Equipment

FAT should show what passed, what failed, and what remains open. IEC 62381 provides a framework for project-specific acceptance testing of process-industry automation systems. It is useful when planning controls tests; it is not a blanket certification of every mechanical, hygienic, or safety feature on a filling line.

What Our Engineers Test

Agree the checklist before the test. Identify the machine, configuration, product, packaging, utilities, target speed, and acceptance criteria. The following items provide a practical starting point for a filling-machine FAT.

CheckRecordAcceptance basis
Mechanical conditionAlignment, mounts, accessible fasteners, guards, leaks, and relevant assembly checksApproved drawings and equipment-specific inspection criteria
Electrical and protective functionsApplicable electrical checks and controlled tests of interlocks, emergency stops, reset, and restartApproved design and procedures, tested by qualified personnel
Controls and motionPLC/HMI versions, recipes, sensor response, servo settings, and sequence behaviorAgreed operating sequence and fault response
Filling performanceResults by head, product conditions, target quantity, speed, measurement method, and samplesAgreed accuracy and repeatability limits
Feeding and transferProduct supply, container positioning, and upstream/downstream interactions included in the testDefined line interfaces and test scope
Sustained operationTime, speed, accepted output, rejects, stops, alarms, and adjustmentsAgreed run conditions and interruption rules
Changeover and cleaningRequired steps, access, fitted parts, settings, and cleaning checksAgreed product and packaging range and procedure

For a single-head servo gear-pump filler, record the selected recipe, feeding conditions, and fill results. For a six-head gear-pump filling machine, identify results by head so a line average does not hide one head’s variation.

Protective-function tests need qualified personnel and controlled conditions. Include a check that resetting an emergency stop only prepares the machine for restart; it should not start motion by itself. Follow the approved design and test procedure.

Our filling accuracy testing guide covers measurement methods. Set the sample count and acceptance limits in the test plan. If weighing a volumetric fill, account for container tare and use product density at the relevant temperature when converting net mass to volume.

Keep speed and accuracy in the same record. A good result at reduced speed does not answer a requirement specified at the production rate. The time-based versus volume-based filling guide explains how dosing method and operating conditions affect the comparison.

Simulating the Customer’s Factory

Use actual bottles, caps, and product where practical. Record the product temperature and relevant handling conditions. If a substitute is needed, agree why it is suitable and what still needs checking with the actual formulation.

Matching viscosity alone may leave differences in foaming, stringing, particles, lubrication, or temperature response. Water is useful for some leak, flow, and function checks, while cream filling needs a representative performance test. Mark the difference clearly in the report.

Packaging details matter too. An airless bottle filling assessment has different questions from a spout-pouch filling assessment. Supply drawings and enough samples to support setup, testing, and agreed repeat checks.

If the project includes a pouch filling and capping machine, test the specified pouch and spout. If it includes a four-wheel capping machine, agree how closure performance will be checked with the actual bottle and cap combination.

Product feeding also affects the test. A rotor-pump filler with an agitator hopper needs its feeding and mixing settings recorded. Our rotary lobe pump filling guide explains the product-handling questions to include.

Record the Continuous Run

Choose the run duration from the equipment duty, test objectives, available product, and agreed risks. Record elapsed time, actual running time, speed, accepted output, rejected output, alarms, stops, and adjustments. Define what happens to the test after an interruption or setting change.

A video helps buyers see the operation. Raw measurements and a signed report show the acceptance result. Keep both linked to the machine identification and tested configuration.

When a Small Adjustment Prevents a Bigger Problem

A Problem Found Before Shipment

During a continuous run, our engineer found an intermittent timing difference of roughly 0.18 seconds associated with the eighth filling head. A brief demonstration could have missed the issue. Sustained operation gave the team time to identify and investigate it.

The finding was specific to this machine’s sequence. A timing difference can affect coordination, depending on how the controls and mechanical movements interact. The measured delay alone does not show that an error will grow by the same amount on every cycle.

Solving It Before the Machine Leaves

Our engineers adjusted the servo synchronization parameters and PLC cycle timing. They then ran a further six-hour continuous test and rechecked filling accuracy against the agreed specification. The correction and verification were completed in less than a day.

Related Solutions

That six-hour run was the retest used for this project. Future machines need a duration suited to their own test plan. Keep the fault description, revised settings, software version, and retest results with the delivery record so the accepted setup can be identified later.

Factory Acceptance Testing Is Part of the Delivery Plan

Comparing Two Delivery Strategies

Basic checks and a planned FAT answer different questions. Use the comparison below to decide what evidence is needed before release. Testing duration and commissioning time remain project-specific.

ItemBasic power-on and no-load checksAgreed FAT with representative conditions
Main purposeConfirm selected basic functionsVerify specified functions and performance within the test scope
Product behaviorLimited evidence without representative productRecord filling, handling, and relevant product effects
Intermittent faultsShort checks may not reveal themA planned run gives more opportunity to find them
Commissioning preparationMay leave production questions unresolvedProvides tested settings and documented findings for the site team
Long-term reliabilityNot established by these checksStill depends on duty, installation, maintenance, and service history

A completed FAT verifies the agreed scope under the recorded test conditions. Site checks still need to cover shipping condition, assembly, utilities, integration, and operation with the customer’s production materials. The installation mistakes guide explains why a machine can need attention even after a successful factory test.

Total Cost of Ownership

Compare testing cost with the work and risk it addresses. Include test materials, witnessing, corrective work, site commissioning, and support arrangements. The machinery TCO guide provides the wider cost framework, and the lowest-price procurement guide explains how to compare what quotations include.

Site readiness belongs in the schedule. Use the factory utilities checklist to confirm power, compressed air, water, cooling, drainage, and access where applicable. Record any difference between the test utilities and the destination installation.

For a supplied double-pass RO water treatment system, agree its own output and water-quality tests. Our water treatment guide helps define the relevant treatment and distribution questions. A filler’s FAT does not establish the performance of an untested utility system.

What Customers Should Ask Before Buying Any Filling Machine

Ask the supplierWhat to agree before FAT
What will you test?Scope, machine identification, configuration, and applicable documents
What samples do you need?Product, containers, caps, quantities, handling, and any substitute limitations
How will you measure the result?Tools, calibration status, sample method, results by head, and acceptance limits
What does the sustained run include?Speed, duration, output criteria, stop rules, and retest requirements
What happens after a failure?Issue record, correction, affected-function retest, and closure evidence
What will we receive?Report, raw records, agreed videos, configuration backups, manuals, and open-item list
What will happen at our factory?Site readiness, installation scope, SAT, training, and support responsibilities

Ask who will manufacture, integrate, test, and support the equipment. The manufacturer versus trading company guide helps clarify responsibilities when more than one business is involved. Put the agreed answers in the purchase documents.

Remote Witnessing and Shipment Release

Decision Guide

Evaluating a new filling-machine supplier?↓Request an equipment-specific FAT plan, sample report, acceptance criteria, and clear testing responsibilities
Considering early shipment for a launch date?↓Review untested items, production risks, completion responsibility, and written release conditions before deciding
Need evidence of filling accuracy?↓Agree the measurement method and sample plan, then review results by head at the specified product conditions and speed
Unable to send the actual formulation?↓Agree a representative substitute, record its limits, and identify which actual-product checks remain for the site
Cannot attend FAT in person?↓Agree live witnessing, machine identification, camera views, measurement access, raw records, and the report
A fault appears during the continuous run?↓Record it, correct it, review affected functions, and repeat the agreed checks before closing the issue
Preparing the factory for delivery?↓Confirm utilities, access, installation work, SAT, training, and the tested configuration
Comparing quotations on price?↓Include testing, commissioning, support, downtime risk, and the equipment scope in the cost comparison

Remote FAT can be useful when travel is difficult. Agree the agenda, camera views, measurement display, live interaction, and document delivery in advance. The buyer should be able to identify the machine, see the test conditions, ask questions, and review the underlying data.

When a problem appears, record it, correct it, and repeat the affected checks. Review whether the change affects other functions. Open items need an agreed owner and completion plan. Decide whether shipment can proceed from the item’s significance and the written release criteria.

Engineering Support Doesn’t End at Shipment

At handover, provide the agreed operating and maintenance instructions, drawings, spare-part information, test report, and configuration records. Backups may include PLC programs, HMI projects, recipes, and drive parameters, as applicable. Identify versions, access rights, and the supported restoration method.

A parameter file alone may not restore the complete machine after hardware replacement or software loss. Agree what the backup covers and who can use it. After delivery, check the installation and complete the agreed SAT before treating the line as ready for production.

For fault reports, start with the machine identification, alarm, operating conditions, recent changes, and a safe video where possible. Use the mixing-equipment maintenance guide for upstream mixer checks when the issue involves product preparation. Separate a feeding problem from a dosing or control problem before changing settings.

Strivers Machinery can also review symptoms from equipment supplied by others and suggest a diagnostic path where information permits. The available drawings, software access, component information, and safe service arrangements determine what support is practical.

For older lines, the equipment upgrade and retrofit guide helps assess whether a targeted repair or change is appropriate. Include a test plan for the modified functions and their interaction with the rest of the line.

Reliability Is What Customers Need

Good manufacturing, a clear specification, useful testing, and proper installation work together. FAT gives you a chance to find problems and verify corrections before shipment. Agree what will be tested, keep the evidence, and carry the accepted configuration through to site commissioning and maintenance.

Technical References

Later Wang

Later Wang

Production Line Planning & Project Management

Later Wang manages production line planning and project execution at Strivers Machinery, working at the intersection of engineering design and client project timelines. From configuring multi-stage production lines to coordinating delivery schedules, Later ensures that each client's equipment setup — whether a single vacuum emulsifying mixer or a complete filling and packaging line — is planned with precision and delivered on schedule. His project management background helps clients move from initial specification to full production readiness with minimal friction.

Need help selecting the right machine?

  • ✔ Free layout design
  • ✔ OEM & ODM
  • ✔ CE Certified
  • ✔ Global Installation
Get Free Quote
This field is required.
This field is required.
If you are not sure, just tell us what products do you produce.
This field is required.
Please check the box to confirm you agree to our Privacy Policy and Cookie Policy before submitting.

How to Plan and Review a Filling Machine Factory Acceptance Test

1
Agree the Test Scope
Identify the machine, configuration, supplied functions, required documents, responsibilities, and acceptance criteria
2
Prepare Product and Packaging Samples
Provide agreed product, bottles, caps, and quantities, documenting any substitute materials and their limits
3
Confirm Test Conditions
Record utilities, product conditions, fill quantity, target speed, run duration, sample plan, and measurement equipment

Frequently Asked Questions

What is Factory Acceptance Testing (FAT)?+
Factory Acceptance Testing is a structured verification process performed at the manufacturer's facility before equipment ships, confirming the machine meets performance, safety, and quality standards under conditions that resemble real production use.
Why is pre-shipment machine testing important?+
Testing before shipment catches mechanical, electrical, and calibration issues while they're still cheap and fast to fix, rather than discovering them after installation, when the same issue can cost weeks of commissioning delay and significant lost production.
How long should a filling machine be tested before shipment?+
It depends on machine complexity, but a thorough FAT for equipment like a servo piston filling machine commonly takes several days, covering mechanical, electrical, and continuous run verification rather than a brief power-on check.